Electricity
Pour installer l'arrivee du courant electrique sous terre, on a du utiliser un gros marteau piqueur pour ouvrir le sol gele.
Murs
Les murs en placo sont installes. Ce sera fini d'ici jeudi.
Foam
Isolation faite. De la mousse a ete projete sur les murs exterieurs creant une barriere thermique.
Tuesday, December 22, 2009
Ikea
Hier, longue journee a Ikea a Boston. La cuisine est commande et tout un tas d'autres meubles a installer. On a achete 1,5 tonnes de meubles! Livraison pour debut Janvier.
Monday, December 21, 2009
This week will change the house
This weekend was the mad wiring project. Everything had to be done so they can complete the insulation and start installing the sheetrock...walls will be done Friday!
Ce weekend cablage des murs de folie. Tout devait etre fini hier soir pour que l'isolation puisse etre finie ce soir. Demain le placo commence. Les murs seront finis vendredi !!youpiii
Sunday, December 20, 2009
quick visit of the house
Friday, December 18, 2009
Friday is 'isolation'
Aujourd'hui c'est isolation. De la mousse isolante est appliquée sur les murs.
Thursday, December 17, 2009
Wednesday, December 16, 2009
Wednesday evening
L'isolation est prevu pour demain et vendredi. Placo pour lundi.
Wednesday evening and we are still on schedule. The Code inspector came this afternoon and he was satisfied with the work being done. We can close the walls.
The electrician still has a lot to do and the plumber team needs to install the piping for the heating system. The septic isn't finished yet. And I am working on speaker wires and other good stuff...
Insulation is scheduled for tomorrow afternoon and Friday. Sheetrock for Monday.
Dave just finished an interesting structure
IKEA est le fournisseur officiel de nos meubles de cuisine. Dave vient de finir une structure qui acceuillera un meuble. Il a eu du mal a le faire pour etre sur que le meuble rentre bien et fasse beau.
Last run
Electricians, plumbers are all going light speed...
Here John Lotfey from Lotfey Electric working in the kitchen and Tim working on the stairs.
Tuesday, December 15, 2009
Monday, December 14, 2009
Monday December 14, 2009
On est en ligne avec le planning. Dave Dardano est content de son equipe et esperons que tout va rester dans les temps.
Window on top of the stairs
The week is starting well.
The plumbing team is in action. Inspection is scheduled for Thursday. Justin from the Town of Falmouth stopped by today and looked happy with what he saw. Nice to work with him.
John Lotfey and the team of Lotfey Electric arrived this afternoon and are going from the top floor down. They are also scheduled to be done by Wednesday evening.
Emery of C&E Earthworks was also hard at work. He has a lot of things on his list this week between the underground service, septic system and other things to move around the house.
And I am working on wiring for speakers and other good stuff.
Friday is insulation. We need to be on schedule.
Friday, December 11, 2009
Les problemes de robinets
Faucets problems
Many years after water and money still come down the drain...
Plumber in action
Voici un des membres de l'equipe plomberie. Todd. Et vu qu'il a l'air d'avoir froid, ca tombe bien, c'est lui qui installe le chauffage.
Made in...
Wednesday, December 9, 2009
Wednesday = neige
Tempete de neige. 36 cm... L'equipe Dardano travaille dedans.
Du retard est pris sur le travail a l'exterieur par contre.
Tuesday, December 8, 2009
Monday December 7
Snow on the ground since Saturday. The team got surprised and they are now working hard on the roof to beat the next snow storm on Wednesday.
Sunday, December 6, 2009
Change of plan
How about a gingerbread house?
Saturday, December 5, 2009
Thursday, December 3, 2009
Jeudi
Today we picked faucets, bathroom stuff, etc.
Tomorrow, end of roof work. Next week, earth work around and plumbing...
De la pluie ce matin, beaucoup d'eau. Donc pas d'activite sur le chantier. Hier etait une grosse journee donc repos merite!
Aujourd'hui nous avons choisi les robinets et les accessoires de salle de bain.
Demain le travail reprend. La semaine prochaine, le terrassier arrangera autour de la maison ainsi que la fosse septique. Et le plombier commence.